Background
This is the third Sprint we plan on this platform. Aim of the sprint was the but fixing of the version 1.9.1-pre (now released as 1.9.1-final) and the work on the new API layer. It has showed a Sprint velocity of 1d/week (based on only tracked and estimated time, it is more) so it is comparable to previous sprints (altough we completed more issues we were also more dev).
...
Nevertheless some insights can be grabbed by the following charts (no longer available once the Sprint is closed, I don’t know the why):
...
Retrospective
During next Webex call we’ll discuss briefly the following 3-points table:
Start doing | Stop doing | Keep doing |
---|---|---|
|
|
|
Action items
After this Sprint will follow
- New Sprint #4 Alessandro Domanico