Sprint Duration: 21 days (from 03/Mar/20 - 24/Mar/20) - hours worked: 1d 3h 30m - developers: 14
Full report @ https://openhospital.atlassian.net/secure/RapidBoard.jspa?rapidView=3&projectKey=OP&view=reporting&chart=sprintRetrospective&sprint=5
Background
This is the third Sprint we plan on this platform. Aim of the sprint was the but fixing of the version 1.9.1-pre (now released as 1.9.1-final) and the work on the new API layer. It has showed a Sprint velocity of 1d/week (based on only tracked and estimated time, it is more) so it is comparable to previous sprints (altough we completed more issues we were also more dev).
It is hard to estimate the real amount of work because of different reasons:
not all people track their workload
Jira has some problems in evaluating tasks progress when organized in different sub-tasks
it has not a unique instrument to evaluate the issues involved in a Sprint
Nevertheless some insights can be grabbed by the following charts (no longer available once the Sprint is closed, I don’t know the why):
Retrospective
During next Webex call we’ll discuss briefly the following 3-points table:
Start doing | Stop doing | Keep doing |
---|---|---|