Sprint Duration: 122 days (from 04/Nov/20 to 29/Apr/21) - hours worked: >100h - developers: 10
Full report @ https://openhospital.atlassian.net/secure/RapidBoard.jspa?rapidView=3&projectKey=OP&view=reporting&chart=sprintRetrospective&sprint=11

Page Properties

...

This Sprint has been huge, so huge that has been retraced and closed many weeks after the planned completion date. Aim of the sprint was the release 1.11 (including the epic “First Release Kidane Mehret Project (Adwa)” (DONE) and the API-Beta (still IN PROGRESS). We decided to close it and start a new one specific for the release 1.11, including a number of issues that have been raised and that are very important to close for an overall code stability.

...

Anyway, as showed in the graphs below, we worked a lot, not only on the tasks involved in the Sprint itself but also on a lot of tasks that will be included in the next version 1.11 changelog, so we worked in the right direction anyway.

...

Retrospective

During next Webex eMeeting call we’ll discuss briefly the following 3-points table:

...