Date
Participants
Agenda
The main project roadmap and the tools
Sprint n.6: what will include the release 1.11.0?
New React User Interface and its Continuous Integrated development (with Cypress CI)
www.open-hospital.org
Discussion topics
Time | Item | Presenter | Notes |
---|---|---|---|
21:00 | Presentations | All | Participants introduced themselves |
21:15 | The main project roadmap | We went through the OpenHospital roadmap, since version 1.8.4 (monolithic, hosted on SourceForge) to the 1.10.0 (multi-component, hosted on GitHub) and its reduced technical debt, thanks to the hard community work, and by finalizing the two Epics goals “Vezo” and “Adwa”. | |
21:45 | v1.11.0 | All | What is missing to release 1.11.0? We briefly discussed the current Sprint n.5 is about to be closed with its OP-06 almost done David B Malkovsky and Emerson Castaneda are working on it. After that we will open Sprint n.6, and the duration will be sized on the previous 3 sprint velocity, for a maximum of 2 months. This Sprint will include:
|
22:30 | React Frontend “ui” | Henrique and Riccardo presented the ongoing developments of the new “ui” which issues are enclosed in a dedicated kanban For its developments the API have been updated to the latet OP-6 branch and are available online at https://www.open-hospital.org/oh-api/swagger-ui.html For developing purposes it is suggested to disable web-security in the browser (see example for Chrome). In the future the back-end Spring Security should be adjusted https://openhospital.atlassian.net/browse/OP-306 | |
22:50 | www.open-hospital.org | The actual website is not updated since many months, probably to a lack of time and/or WordPress awared people. Also, at the moment it is missing an accountable person for it. A proposal could be to move the website under a repository and to have a minimum (or eventually complex) website on GitHub pages which code would be hosted as any other project's code (example here and here) and to manage changes with issues and PR; this would transfer the website ownership back to the project's opensource community itself. The group has raised doubts about segregations of competencies and roles between project coding and project marketing. |
Action items
- Alessandro Domanico to create an issue about the “automatic announcer”
- Alessandro DomanicoDavid B MalkovskyEmerson Castaneda to solve problems in OP-6 so we can close Sprint n.5
- Alessandro Domanico once closed Sprint n.5, produce retrospective and open Sprint n.6