This is the second Sprint we plan on this platform, and the first one () has showed a working capacity of 1.15days/week, so we planned it for an amount of issues of 3d 6h (Estimated Time) considering 3 weeks = 3.55days.
Retrospective
The present retrospective is about the 2nd Sprint we had, starting January 2020, which aim was ”To have a full implementation of REST API while keeping the "gui" up and running, plus some enhancements coming from unplanned issues and tickets (bugs)”.
...
The focus factor this time has been 0 (if counting the closed issues, less than 0.025 if we count worked hours) so the average with the previous one is (0 + 0.058) / 2 = 0.029 => 0,575 d/week, means that for the next Sprint we cannot plan more than that amount of work for the team per week (next Sprint of 3 weeks = 1d 6h)
We should then:
Step1: to finish bugfixing on 1.9.1-pre and release 1.9.1
Step2: to merge 1.9.1 fixes on ‘default/master/develop’ branches and repeat the Sprint for the 1.9.2-pre:
Also: for each new releases, we should branch and create a new branch X.Y.Z so both release and bugfixing can go at their own pace.
...
Start doing |
---|
...
Stop doing |
---|
...
Keep doing |
---|
...
Start doing
...
Stop doing
...
Keep doing
Action items
|
|
|
Action items
- Alessandro Domanico to provide CONTRIBUTING files on GitHub repositories
- Alessandro Falezza to provide more documentation about “ui” working cases