Date

Team

OpenHospital Core Team

Participants

Alessandro Domanico Vito Romano

Background

First Sprint of the OpenHospital working group, with the aim “To have first release containing all components "core", "gui", "api" and "ui" working together with a minimum functionality of "ui" (only new-patient and search-patient)”.

Retrospective

The time was enough but the team focus factor was not yet tested and many issues remained unresolved.

...

Start doing

Stop doing

Keep doing

  • To use the last 3 sprints average velocity to plan the current sprint

  • To inform the SM (SCRUM Master) if any deadlock occurs in the issue assignment

  • Planning what is not possible to achieve

  • Documenting issues has been the best part in having some issues closed.

Action items

  •  To document any finding under the issues
  •  To hit the community for help and to foster the online discussion
  •   To inform the SM (SCRUM Master) if any deadlock occurs in the issue assignment