This is the second Sprint we plan on this platform, and the first one () has showed a working capacity of 1.15days/week, so we planned it for an amount of issues of 3d 6h (Estimated Time) considering 3 weeks = 3.55days.
Retrospective
The present retrospective is about the 2nd Sprint we had, starting January 2020, which aim was ”To have a full implementation of REST API while keeping the "gui" up and running, plus some enhancements coming from unplanned issues and tickets (bugs)”.
...
Start doing | Stop doing | Keep doing |
---|---|---|