The focus factor this time has been 0 (if counting the closed issues, less than 0.025 if we count worked hours) so the average with the previous one is (0 + 0.058) / 2 = 0.029 => 0,575 d/week, means that for the next Sprint we cannot plan more than that amount of work for the team per week (next Sprint of 3 weeks = 1d 6h)

We should then:

  • Step1: to finish bugfixing on 1.9.1-pre and release 1.9.1

  • Step2: to merge 1.9.1 fixes on ‘default/master/develop’ branches and repeat the Sprint for the 1.9.2-pre:

    • to approve or change OP-178

    • to approve or change OP-127

    • to define a pattern for OP-6

    • to solve small big yet unresolved issues for 1.9.1

...